PMP câu hỏi số 1
PMP câu hỏi số 1
HHoa Nguyen·1 câu hỏi
1
A project manager for a predictive project has received the following email from a key stakeholder: From: Marketing Director To: Project Manager Subject: Urgent: New Feature for Campaign Launch Hello, Our executive team has decided to add a real-time social media analytics feature to the product. It is critical for the upcoming campaign. Please have your team start working on it right away. We can discuss the budget and schedule impact next month after we see how it goes. Since this came from the executive team, I’m assuming we don’t have to go through the change process. Thanks, Marketing Director Using the information in this email, what should the project manager do first?